Parts of northern Chongqing lost supply while the Panxi project connected new and existing mains. The report listed 19 connections, with pipes up to 1.8 metres across, and installation or replacement of 31 gate valves. The utility also used the shutdown to clean clear-water storage and the distribution well at Liangtuo Waterworks.
Engineering takeaway Plan site drainage, connection work and confirmation of restoration in each service zone.