Foshan begins the northern section of a Sanshui water main

Illustrative transmission main construction in rural Guangdong
Illustrative scene

Main construction begins ·

Work began on the Beijiang Waterworks-to-Liugang section, the first of three northern packages on Sanshui’s north–south trunk main. The utility planned to link the northern packages before December, in time for the plant’s expected start-up at year-end. About 13 km of southern main had been linked before the Lunar New Year. Unserved villages were concentrated in central and northern Sanshui.

Engineering takeaway Track main commissioning, branch connections and completed household connections separately.