Lanbo Water Tanks
← Water infrastructure daily

Emergency trial transfer to Tianjin ends on the eastern route

Raw-water transfer canal and gate in Tianjin
Illustrative scene

Source-water security ·

The emergency trial of the eastern route’s northern extension ended on 25 June 2019. Water travelled about 487 km from Shandong’s Dongping Lake to Tianjin via the South Canal. Tianjin’s water authority reported a 66-day run and 19.78 million cubic metres received at Jiuxuan Gate. The trial tested route operation and provided replenishment for some rivers, reservoirs and aquifers.

Engineering takeaway Log trial volumes, timing and operating conditions at the upstream and downstream control points.

Source China National Radio