The Cihuai New River intake booster station for the Taihe project topped out on 27 June, moving the work from civil construction to mechanical and electrical installation. PowerChina’s design calls for eight centrifugal pumps and 10.5 cubic metres per second. Two pressure mains are planned to deliver water towards Taihe, Jieshou and Linquan.
Engineering takeaway Confirm pump foundations, inlet and outlet connections and access before equipment installation.