Wuhan estate plans a phased water cutover as Fuzhou completes main renewal
An estate of 1,325 households in Wuhan is laying a new supply main ahead of a phased cutover. Fuzhou renewed 720 metres of water main, and Shenzhen’s Bao’an utility published bid evaluation results for pump room safety work.
Illustrative scene
Work in progress ·
Wuhan’s Xin’ao Yijiangpanyuan estate lays a new main for a phased cutover
Xin’ao Yijiangpanyuan, a 1,325-household estate in Wuhan’s Qingshan District, has ageing distribution pipes and reported pressure fluctuations on upper floors. Work began in late July, and crews were laying the estate’s new main when the report appeared. The project also covers building risers, the booster pump room and individual household meters. Existing pipes will supply residents until buildings are ready to switch in batches, with completion expected by the end of 2026.
Engineering takeaway For a phased cutover, record isolation points between old and new pipes, pressure-test and flushing results, shutdown and restart notices, and upper-floor pressure for each building before it changes over.
Fuzhou completes 720 metres of DN800 water main renewal on Jin’an Middle Road
The section of Jin’an Middle Road from Fuxin Branch Road to Tatou Road carries water between Fuzhou’s Gulou and Jin’an districts. Fuzhou Water Supply Company coordinated replacement of about 720 metres of DN800 water main with stormwater and sewer work along the same route. Crews worked in sections of about 50 metres and finished the 30-day project with the road surface restored on November 13.
Engineering takeaway When water and sewer work share an excavation window, mark crossing elevations and handover points for water-main pressure tests and backfilling on the coordinated drawings. Agree how each section will be cleared to reopen.
Shenzhen’s Bao’an utility publishes provisional result for pump room safety work
Shenzhen Shenshui Bao’an Water published its evaluation results for a 2026 safety remediation service covering domestic booster pump rooms. Three invited firms submitted quotations on time. Shenzhen Hengxiang Decoration is the provisional selection at CNY 122,753.55, subject to a three-day notice period during which objections may be filed.
Engineering takeaway For pump room safety work, use a room-by-room checklist for access routes, slip hazards and standing water, and equipment service clearance. Keep a follow-up inspection record for each item.