Engineering scenario
Xuzhou · Underground collection and pumped drainage
Confirm sump elevations, pump head, standby operation, alarms and lifting and cleaning access.

Checks and records
- Operating conditions
- Put inlet, stop, start, alarm and overflow elevations on one section drawing.
- Site coordination
- Use the approved test plan to check lead/standby changeover, alarms and recovery after power interruption.
- Commissioning
- Record measurements, alarm destinations, reset steps and follow-up ownership.